A project manager has received numerous complaints from staff concerning poor service provided by a vendor.
Which of the following steps should the project manager take FIRST to correct the problem?
Which of the following steps should the project manager take FIRST to correct the problem?
Notify the key stakeholders of the problem and send a C&D letter to the vendor
Notify the vendor of the complaints and review the SLA with the vendor
Review the acceptable use policy with the vendor before requesting termination of the vendor s employee.
Project Constraints
Communication and Change Management
A project manager has requested the procurement department collect detailed solutions with cost estimates from qualified third-party vendors.
This is an example of an:
This is an example of an:
MOA
RFP
RFI
RFQ
MOU
Project Basics
Project Tools and Documentation
A project manager has set aside a contingency reserve for unforeseen communications. Which of the following types of communication is MOST likely to utilize this contingency reserve?
Impromptu meeting
Closure conference
Distributed printed media
Kickoff meeting
Communication and Change Management
A project manager has taken over a project that is already in progress. The project manager notices the functional manager of one team is unaware of the current progress. Which of the following should the project manager do? (Choose two.)
Update the project charter to include the functional manager as a key stakeholder
Publish the project schedule to the functional manager
Review the communications plan to ensure proper involvement
Add the incident to the issue log and seek resolution
Ensure the functional manager is on the status report distribution list
Communication and Change Management
Project Tools and Documentation
A project manager has updated the project schedule but cannot analyze the schedule performance. Which of the following steps did the project manager miss?
Lock the schedule
Approve the schedule
Baseline the schedule
Fast track the schedule
Project Scheduling and Cost Management
A project manager has updated the risk register with the current risk status, probability, and impact. Risk IDs 2 and 6 have now been realized.
Which of the following is the NEXT appropriate step for the project manager to take?
Which of the following is the NEXT appropriate step for the project manager to take?
Identify risk strategies for the realized events
Change the risk status to closed for 2 and 6
Consult the risk management plan
Update the issue log
Risk Management and Quality Assurance
A project manager has updated the risk register with the current risk status, probability, and impact. Risk IDs 2 and 6 have now been realized.
Which of the following is the NEXT appropriate step for the project manager to take?
Which of the following is the NEXT appropriate step for the project manager to take?
Identify risk strategies for the realized events
Change the risk status to closed for 2 and 6
Consult the risk management plan
Update the issue log
Risk Management and Quality Assurance
A project manager in a function organization is resource leveling the upcoming phase. The project manager notices one of the resources is assigned with 20% of allocation to a secondary project. This situation limits and jeopardizes the commitment date.
Which of the following should the project manager do NEXT?
Which of the following should the project manager do NEXT?
Ask the PMO to mitigate the risk related to insufficient resources.
Ask the functional manager to provide a resource with the same level of allocation.
Remove 20 of allocation of the resource from the secondary project.
Ask the resource to improve performance to target with commitment date.
Project Constraints
A project manager is analyzing the cost variances produced when comparing two different projects completions.
Which of the following factors could be causing the increased variance for the four-month projects? (Choose two.)
Which of the following factors could be causing the increased variance for the four-month projects? (Choose two.)
Increased resource productivity
Increased resource allocation
Increased schedule variance
Increased labor cost
Increased labor overhead
Project Constraints
Project Scheduling and Cost Management
A project manager is analyzing the cost variances produced when comparing two different projects completions.
Which of the following factors could be causing the increased variance for the four-month projects? (Choose two.)
Which of the following factors could be causing the increased variance for the four-month projects? (Choose two.)
Increased resource productivity
Increased resource allocation
Increased schedule variance
Increased labor cost
Increased labor overhead
Project Scheduling and Cost Management
Risk Management and Quality Assurance