Exam Logo

Comptia (PK0-004) Exam Questions And Answers page 45

During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB.


Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?
Risk Management and Quality Assurance
During a risk review session, the project team identified the percentage probability that a particular risk will occur. This is known as:
Risk Management and Quality Assurance
During a routine risk review, the project champion analyzes the status of multiple projects. A potential risk is discovered that will delay project A due to the interdependencies with project B. The project champion schedules a meeting with the project managers. Which of the following risk activities is MOST likely happening?
Project Constraints Project Scheduling and Cost Management
During a weekly meeting, a project manager mentioned a decision was made on June 17 to include future state workflows in onboard training.

Which of the following communication methods should be used?
Communication and Change Management
During planning, a project coordinator publishes the project management plan. After reviewing the plan, the project sponsor is concerned it is too long and detailed. Which of the following does the project sponsor desire?
Project Constraints Communication and Change Management
During the execution phase of a project, a project task has run longer than anticipated.


Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
Project Scheduling and Cost Management
During the execution phase of a project, a project task has run longer than anticipated.


Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
Project Scheduling and Cost Management
During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor s tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months.

Which of the following should have occurred to prevent this issue?
Project Constraints Communication and Change Management
During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project.

Which of the following documents would contain these items?
Project Basics
During the planning phase of a construction project, the project team discovers the site is the nesting area of rare birds, and construction could disrupt the birds' patterns. Lobbyists would like the team to move the project down the road.

Which of the following constraint and influencer types are involved in this scenario?
Project Constraints Risk Management and Quality Assurance