Comptia (PK0-004) Exam Questions And Answers page 51
Risk ID 2 has occurred.
Which of the following ways should the project manager update the risk register?
Which of the following ways should the project manager update the risk register?
Change the risk 2 response to backups restored
Change the risk 2 status to issue
Change the risk 2 owner to PM
Risk Management and Quality Assurance
Several team members report that meeting objectives are not being met.
Which of the following documents would a project manager create to make team meetings more effective? (Choose two.)
Which of the following documents would a project manager create to make team meetings more effective? (Choose two.)
Create an SOW prior to each meeting and adhere to it.
Create a meeting agenda prior to each meeting and adhere to it.
Create a lessons learned list prior to each meeting and adhere to it.
Create a project charter prior to each meeting and adhere to it.
Create an action item list during the meeting and adhere to it.
Create a corrective action plan prior to each meeting and adhere to it.
Create a WBS prior to each meeting and adhere to it.
Communication and Change Management
Project Scheduling and Cost Management
Severe weather has impacted a construction project, delaying scheduled work for five days. Which of the following project changes is the project manager most likely to consider FIRST?
Requirements change
Funding change
Timeline change
Risk event
Project Scheduling and Cost Management
Stakeholders often do not understand the hierarchy of roles and responsibilities on a project team. Which of the following could provide a visual representation?
Work breakdown structure
Milestone list
Organizational chart
Action items
Communication and Change Management
Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3. Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a duration of one day. Which of the following represents the critical path?
Five days
Six days
Seven days
Eight days
Project Scheduling and Cost Management
Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:
Managing change
Fast tracking
Rolling wave planning
Crashing
Communication and Change Management
Project Tools and Documentation
Task ID 3 did not start on time, and no work has been accomplished yet. Evaluate the schedule below:
Which of the following is MOST likely the cause?
Which of the following is MOST likely the cause?
Predecessors not properly identified
Scope change
Retrospective in progress
Insufficient resources assigned
Project Constraints
Project Scheduling and Cost Management
Task ID 3 did not start on time, and no work has been accomplished yet. Evaluate the schedule below:
Which of the following is MOST likely the cause?
Which of the following is MOST likely the cause?
Predecessors not properly identified
Scope change
Retrospective in progress
Insufficient resources assigned
Project Scheduling and Cost Management
Tasks A and B have a duration of two days. Task A starts on Day 1, and Task B starts on Day 3. Tasks C and D have a duration of three days, and Task E has a duration of four days. Task C starts after Task A. Task D and E start after Task C. If Task A starts on December 15, which of the following is the anticipated start date for Task D?
December 18
December 19
December 20
December 21
December 22
Project Scheduling and Cost Management
Tasks A, B, and C have a duration of two days. Task D has a duration of three days, and Task E has duration of four days. Task A starts on Day 1, and Task B starts on Day 2. Task C starts after Task A. Tasks D and E start after Task C. Which of the following is the critical path if Task B starts on Day 3?
A, C, D
A, C, E
A, D, E
B, C, E
Project Constraints
Project Scheduling and Cost Management