Risk ID 2 has occurred.


Which of the following ways should the project manager update the risk register?
Risk Management and Quality Assurance
Several team members report that meeting objectives are not being met.

Which of the following documents would a project manager create to make team meetings more effective? (Choose two.)
Communication and Change Management Project Scheduling and Cost Management
Severe weather has impacted a construction project, delaying scheduled work for five days. Which of the following project changes is the project manager most likely to consider FIRST?
Project Scheduling and Cost Management
Stakeholders often do not understand the hierarchy of roles and responsibilities on a project team. Which of the following could provide a visual representation?
Communication and Change Management
Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3. Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a duration of one day. Which of the following represents the critical path?
Project Scheduling and Cost Management
Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:
Communication and Change Management Project Tools and Documentation
Task ID 3 did not start on time, and no work has been accomplished yet. Evaluate the schedule below:


Which of the following is MOST likely the cause?
Project Constraints Project Scheduling and Cost Management
Task ID 3 did not start on time, and no work has been accomplished yet. Evaluate the schedule below:


Which of the following is MOST likely the cause?
Project Scheduling and Cost Management
Tasks A and B have a duration of two days. Task A starts on Day 1, and Task B starts on Day 3. Tasks C and D have a duration of three days, and Task E has a duration of four days. Task C starts after Task A. Task D and E start after Task C. If Task A starts on December 15, which of the following is the anticipated start date for Task D?
Project Scheduling and Cost Management
Tasks A, B, and C have a duration of two days. Task D has a duration of three days, and Task E has duration of four days. Task A starts on Day 1, and Task B starts on Day 2. Task C starts after Task A. Tasks D and E start after Task C. Which of the following is the critical path if Task B starts on Day 3?
Project Constraints Project Scheduling and Cost Management